摘要
针对摩托车包装作业线上各工序之间不均衡且存在大量等待时间的现象,以动作经济原则和“ ECRS冶四大原则为指导,结合生产线平衡理论,运用模特法对包装线上的瓶颈工序进行了分析,根据分析结果设计了相应的改善方案。 方案的实施使生产线平衡率提高了 22. 2% ,生产节拍降低了 5. 43 s。
Abstract
A lot of idle and waiting time exists among some workstations in motorcycle packaging line. Aiming at this phenomenon, the bottle-neck section of packaging line was studied using MOD method. According to the principle of motion economy, the principles of ECRS and the theory of assembly line balance, a new scheme was put forward. Implementation of this new scheme makes the rate of production line balance upgrade 22. 2% and the cycle time decrease 5. 43 seconds.
侯东亮.
基于模特法的摩托车包装生产线平衡[J]. 包装工程(技术栏目). 2012(21): 137-141
HOU Dong-liang.
Motorcycle Packaging Line Balancing Based on MOD[J]. Packaging Engineering. 2012(21): 137-141